Industrial : Greenham's Pallet Freezer

Bacon Factory Road, Smithton TAS 7330

Greenham's new 512 pallet freezer at their Smithton factory which was completed in November 2015 after a 6 month construction time. Greenham's entered into a Design and Construct contract with Stubbs Constructions Pty Ltd for this project with the construction involving driven timber piles, concrete/blockwork footings, concrete slabs, steel structure with insulated panels. Part of the design also required a 3m high fire wall to separate the new building from the existing infrastructure this was accomplished using 150mm thick precast panels. Once the cool store was constructed Stubbs Constructions Pty Ltd were also selected for the design and installation of the pallet racking system that was used.

Project Points

  • Design & Construct
  • Contract Value $1.7 M
  • Design & Installation Pallet Racking System