construction - Industrial
 
Back to site page...
Print Friendly...
 
     
  Job title :
Glaxo Smith Kline – Concrete Works
 
     
 

This Project awarded to Stubbs Constructions Pty. Ltd. in a competitive tender environment. This Project involved the construction of a 4,500 m2 storage building. The head contract was managed by Tasmanian Consulting Service, with Stubbs Constructions Pty. Ltd. completing the piling, footings, and concrete panels.

Due to poor ground conditions, steel piles were required at column locations. These were installed using an excavator mounted hydraulic pile driver.

A total of 150 m2 concrete was formed, placed & finished in the in-situ concrete footings. It was critical to the overall construction process that the hold down bolts for the columns be installed in these footings with a tolerance of only 2 mm. This was achieved, with all cast-in items correctly installed.

The major part of Stubbs Constructions Pty. Ltd. work was the manufacture & installation of 70 No. pre-cast panels. The large 200 mm thick panels were manufactured on site, being cast on specially made casting beds. The smaller panels were constructed at our River Road per-cast facility. Due to the panels have a natural unpainted finish the finish was of a very high standard.

The panels were installed by Stubbs Constructions Pty. Ltd. utilising mobile hydraulic cranage. The Project required that the panels be installed with the smaller panels stacked on top of the larger ones.

 

 

 
     
© Copyright 2004, STUBBS CONSTRUCTIONS PTY LTD.
 
     
Home Page | Contact us | Privacy Statment | Construction | Projects | Resources | Management | History
Stubbs Constructions Pty Ltd - 15 River Road, Wivenhoe, TAS 7320,
PO Box 573, Burnie TAS 7320.
Phone: (03) 6431 3306 / Fax: (03) 6431 6238